Family Fitness Center Updates

Week of OCt. 3RD Updates

– South parking lot finished and striped
– Road Patching on 165 south
– Accent stripes on the walls of the gym
– Glass going in on north side of level 2
– GFRC panels going up 
– Screen walls being welded.
– Fire risers for deluge system
– Painting racquetball courts

Week of Sept. 21st Updates

-South parking lot paving work
-Patch road 165 South
-Light poles poured in south lot
-Utilities completed
-Testing hydrants
-Prepping for frames and glass on 2nd floor
-Completed gym wall painting
-Multi-purpose room lighting
-Electrical rough in continuing

Week of Sept. 14th Updates

-West side sidewalk completed
-West side speed table added
-Lighting added to the west lot/entrance
-GFRC column covers going up
-Painting gym walls
-Working on electrical in the gym (lights, fire alarm, air pears, etc)
-Glass windows installed on the first floor
-Working on electrical rough in throughout the building
-Working on painting throughout

Week of Sept. 7th Updates

-Pools re-opened on Tues, Sept 8
-Leisure pool health department permits issued
-Pool area glass doors finished
-Interior handrail install completed
-Glass window frames installed on north side of 1st and 2nd floors
-Electrical rough in on level 1 started
-Rough grading of south lot for asphalt
-Utility work on south side of building completed

Week of Sept. 1 Updates

Week: Sept. 1 – 5:

-Temporary vestibule west entrance built
-Hot tub plastered and filled
-New HVAC in pool fired up
-Pools filled, heated and treated
-New ADA lift installed
-Lockers installed
-Locker room finishes completed
-Spectator seating windows installed
-Pool area doors installed
-Pool decks cleaned
-Pool area temporary occupancy permits issued
-Pool area temporary fire inspection permits issued
-Lap pool and hot tub health department permits issued
-Interior paint continuing in upstairs cardio/weight areas
 

Week of August 24-29:

-Spectator Seating completion and final walkthrough
-Window framing in pool area
-Mill work and counters in guard room and aquatics office
-Flooring in guard room and aquatics office
-Pool area deck stain
-Pools power wash, inspection and repairs
-Locker room finishes
-Leisure pool exterior paint
-Plyo stairs installed in functional fitness
-Handrail install continuing
-Ceiling paint in gym
-Parking lot striping
-Parking lot landscaping

Aug. 20th Weekly Update

Items completed this week:

-painting pool areas
-installing spectator seating in the pool area
-work on retention basin to the south of the building
-locker room partitions installation
-elevator installation
-handrail installation
-insulation
-drywall
-hvac ductwork
-north parking lot work
-some internal paint